photo
Area 5 excavation
photo
View of Site
photo
West fence line being installed

The latest site activities have included continued preliminary Deep Soil Mixing (DSM) field testing activities, and soil excavation and onsite transportation. The western fenceline of the former MGP site was extended offsite approximately 40 feet to the west to facilitate remediation work in this area. Delivery of components and construction of DSM batch plant #2 started as well as deliveries and assembly of the 2nd DSM drill rig.

A Fact Sheet summarizing the project and potential impacts to the community was previously sent to the community to summarize the work. The Fact Sheet and the finalized Remedial Action Work Plan can also be found in the Key Documents/Major Reports section of this website. A link to the Fact Sheet can be found below. The work is being performed in accordance with the Community Air Monitoring Plan that was reviewed by the New York State Department of Environmental Conservation, New York State Department of Health and the Nassau County Department of Health. There is an on-site NYSDEC representative monitoring the project activities.

As work proceeds, the web site will be updated periodically to ensure the community is informed of the project progress and schedule.


Hempstead Fact Sheet September 2011 in English and Spanish.